0% · 0/25

Glossary

Construction and real estate development terminology you'll hear on every call. Search, skim, and memorize.

AIA pay app
Standardized monthly invoice format (G702/G703) GCs use to bill owners for completed work.
"They submit the AIA pay app on the 25th and we cut the check by the 10th."
ATO (Authority to Operate)
Security authorization required before a system can hold government data.
"We need ATO before we can stand up the platform on this contract."
Bid leveling
Comparing subcontractor bids apples-to-apples by normalizing scope, exclusions, and assumptions.
"Pre-award, the PM does bid leveling on the three mechanical bids before recommending one."
BIM (Building Information Modeling)
Digital representation of a building's physical and functional characteristics. Used for design, construction, and operations.
"The architect's BIM model is the source of truth for clash detection."
Capex (Capital Expenditure)
Money spent on construction or major upgrades, separate from operating expense.
"Their capex budget is $40M this year, split across three campuses."
Capital stack
The layers of financing on a real estate project — senior debt, mezz, preferred equity, common equity. Each layer has different return expectations and reporting requirements.
"Their capital stack on this deal is 65% senior, 15% mezz, 20% equity."
Change order
A documented modification to scope, schedule, or cost after the contract is signed.
"That foundation surprise turned into a $400k change order."
Closeout
The final phase: punch list, warranties, O&M manuals, lien waivers, final pay app.
"We're 90% done but closeout always takes another two months."
CMAR (Construction Manager At Risk)
Delivery method where the CM commits to a guaranteed maximum price and takes on overrun risk.
"They're delivering this one CMAR — different risk profile than design-bid-build."
CMMC (Cybersecurity Maturity Model Certification)
Defense contractor security framework. Required for many DoD-related projects.
"Anyone touching DoD work needs CMMC Level 2 minimum."
COI (Certificate of Insurance)
Document confirming a contractor or sub carries required insurance coverage. Standard pre-mobilization gate.
"We can't let them on site without a current COI on file."
Critical path
The longest sequence of dependent tasks in a project schedule. A delay on any critical path task delays the whole project.
"Steel delivery is on the critical path — every day late is a day late on substantial completion."
Daily log
Daily field record of work performed, weather, manpower, deliveries, and incidents.
"The super logs daily — anything not in the daily log didn't happen."
DD (Due Diligence)
Investigation period during which a buyer evaluates a property or deal before commitment.
"They have 60 days of DD to walk away clean."
Deferred maintenance
Facility work that's been postponed, accumulating as backlog. Common in higher ed and institutional portfolios.
"They've got $300M in deferred maintenance that competes with new construction every budget cycle."
Design-build
Delivery method where one entity holds both design and construction contracts. Faster than traditional, less owner control.
"They went design-build to compress the schedule."
Draws
Scheduled disbursements of construction loan funds tied to completed work and lender approval.
"The lender funds the next draw once the inspector signs off on framing."
EAC (Estimate at Completion)
Forecasted final cost of a project based on actuals to date plus remaining estimate.
"Our EAC is tracking 4% over budget. Need to flag the change orders driving it."
Entitlement
The process of obtaining government approvals (zoning, permits, environmental) needed to develop a property.
"Entitlement took 18 months — twice as long as we underwrote."
FAR (Federal Acquisition Regulation)
The master rulebook for federal government procurement.
"Every change has to be FAR-compliant or it doesn't count."
FedRAMP
Federal cloud security authorization framework.
"They won't even talk to us until we have FedRAMP."
Float
Schedule slack — the amount of time a non-critical task can be delayed without affecting the overall completion date.
"That activity has 10 days of float, so we can shift resources to the critical path without risk."
General conditions
Indirect costs of running a project — site supervision, temporary facilities, equipment, utilities. Usually a percentage of the total contract.
"Their general conditions came in at 8% — high but consistent for a project this complex."
GMP
Guaranteed Maximum Price — contract type capping the owner's exposure; GC eats overruns above it.
"We're working under a GMP, so any overage on steel comes out of their fee."
GSA Schedule
Pre-negotiated contract vehicle administered by the General Services Administration that lets federal buyers purchase from approved vendors faster.
"Without a GSA Schedule listing, federal sales cycles get a lot slower."
Hard cost / Soft cost
Hard costs = physical construction (materials, labor). Soft costs = professional fees, permits, financing, insurance.
"Hard costs are about 75% of the project budget; soft costs cover the rest."
IDIQ (Indefinite Delivery, Indefinite Quantity)
Federal contract type used for ongoing project work where exact quantities aren't pre-determined.
"They're an IDIQ holder — that opens up dozens of task orders."
IFB (Invitation for Bid)
Formal solicitation in public procurement asking vendors to submit sealed bids. Used when requirements are clearly defined.
"They issued the IFB last month — bids are due by the 30th."
IRR (Internal Rate of Return)
The discount rate that makes the net present value of a project's cash flows equal zero. Used to compare investment returns across deals.
"Their underwriting IRR was 22%; they're now tracking closer to 15%."
Joint venture (JV)
A partnership between two or more parties to share ownership and management of a project, typically for capital, risk, or expertise.
"They're doing this one as a JV with a local sponsor — gets them market knowledge they don't have in-house."
LEED
Leadership in Energy and Environmental Design — a green building certification system from the US Green Building Council. Common requirement on institutional and government projects.
"They're targeting LEED Gold, which means a tighter envelope and specific MEP requirements."
Lien waiver
Signed document where a contractor or sub waives the right to file a mechanic's lien for work covered by a payment.
"We don't release the check until we have signed lien waivers from every sub."
LOI (Letter of Intent)
Non-binding document signaling intent to enter into a future contract.
"They sent an LOI for the next phase — contract should follow in 30 days."
Long lead items
Materials or equipment that take significant time to procure and have to be ordered well before they're needed.
"We're 12 weeks out on the switchgear — that's a long lead item we need to order now."
Lookahead
Short-term schedule (usually 2–3 weeks) showing upcoming work, used in weekly OAC meetings.
"Pull up the three-week lookahead — what's blocking trade #4?"
LTC (Loan to Cost)
The ratio of a construction loan to total project cost. Typical lenders fund 65–75% LTC, with the developer covering the rest as equity.
"They got 70% LTC from the senior lender; they're filling the gap with mezz."
Master plan
Long-term plan for campus or portfolio development. Common in higher ed and large institutional clients.
"Their master plan calls for $500M in capital projects over the next decade."
MEP (Mechanical, Electrical, Plumbing)
Building systems supplying heating, cooling, power, water, and waste removal.
"MEP coordination starts in pre-con — clashes between the trades cost millions if caught late."
Mobilization
The activities and costs at the start of a construction project — setting up the site, moving in equipment, hiring labor, establishing logistics.
"We're three weeks from mobilization. Submittal log has to be approved by then."
Mockup
A full-scale or partial-scale physical model of a construction element built to confirm design, quality, and constructability before full installation.
"They're building a brick mockup on site so the architect can sign off before the rest of the facade goes up."
NOI (Net Operating Income)
A property's annual income after operating expenses but before debt service. Core metric for valuing income-producing real estate.
"Once stabilized, NOI projections are $4.2M annually."
NTP (Notice to Proceed)
Formal notification from the owner authorizing the contractor to begin work.
"They got NTP last Tuesday — they're 18 days into a 22-month build."
O&M (Operations & Maintenance)
Documentation, manuals, and procedures for operating and maintaining a building's systems after construction.
"O&M manuals are part of closeout — facilities team won't take handoff without them."
OAC meeting (Owner-Architect-Contractor)
Standing weekly meeting between owner, architect, and contractor to coordinate on the project.
"Decisions happen in the OAC — if you weren't in the OAC, you don't have a say."
Owner's Rep
Third-party hired by the owner to represent their interests during construction. Common on large or complex projects.
"The owner's rep is who we sell to most often — they care about reporting."
Pre-con
Pre-construction: planning phase where scope, budget, schedule, and team are locked in before mobilization.
"We're still in pre-con — no shovels in the ground yet."
Pro forma
Financial model showing expected costs and returns on a real estate project. Updated continuously during construction.
"The pro forma assumed $180/sf hard costs — we're tracking $192."
PSA (Purchase and Sale Agreement)
The contract between a buyer and seller of real estate that lays out terms, contingencies, and timing of the sale.
"PSA was signed last week. Closing is contingent on entitlement."
Punch list
Outstanding minor items the GC must complete before the project is considered done.
"Substantial completion is hit, we're just working through the punch list."
Retainage
A percentage of each pay app the owner withholds (usually 5–10%) until the project is complete.
"They're holding 10% retainage and we won't see it until closeout."
RFI
Request For Information — a formal question from the contractor to the design team.
"There are 47 open RFIs and the GC says they can't proceed on the east wing until they're answered."
RFP (Request for Proposal)
Formal solicitation asking vendors to submit detailed proposals for a project. Common in higher ed and government procurement.
"The RFP dropped Monday. Response is due in 30 days, with a 200-page limit."
RFQ (Request for Quotation)
Solicitation requesting price quotes for clearly defined goods or services. Less detailed than an RFP.
"They sent an RFQ for the AV systems on three projects."
Self-perform
When a GC executes work directly with their own crews rather than subcontracting it. Common for concrete, framing, or other core trades.
"They self-perform concrete — gives them better margin and schedule control."
SoV
Schedule of Values — line-item breakdown of the contract sum used to track progress billing.
"The SoV has 38 line items; they bill against each one monthly."
SOW (Scope of Work)
Document defining the specific work, deliverables, timeline, and pricing under a contract. Common in government and consulting contexts.
"Each task order under the IDIQ has its own SOW."
Stabilization
When a property reaches full occupancy or income — a milestone on most pro formas.
"They underwrote 18 months to stabilization. They're at month 22."
Submittal
Shop drawings, samples, and product data the contractor submits for design team approval before installing.
"The submittal for the curtain wall has been sitting with the architect for three weeks."
Substantial completion
Point at which a project is sufficiently complete for the owner to use it for its intended purpose. Triggers warranties and the closeout process.
"Substantial completion was hit two weeks ago — we're working through punch list now."
TI
Tenant Improvements — interior buildout work done to customize a leased space for a tenant.
"The landlord is funding $80/sf in TI for the new tenant."
Value engineering (VE)
Modifying scope or specifications to reduce cost while maintaining function.
"They came in $2M over budget — VE'd $1.4M out of the lobby finishes."